Free download, CSV for Excel
Measurement sheet template for contractors
A detailed measurement sheet in the measurement book layout: date, BOQ item, location, nos, L, B, D and quantity, with the drawing reference for each row.
Columns and filled rows
All 11 columns, filled from one work order so the arithmetic can be checked. The download opens in Excel, Google Sheets or LibreOffice.
| Date | BOQ item | Location | Nos | L (m) | B (m) | D (m) | Qty | Unit | Drawing ref | Remarks |
|---|---|---|---|---|---|---|---|---|---|---|
| 28-10-2026 | 3.2 | Slab S3, bay 2 to 4 | 1 | 12.40 | 6.20 | 0.150 | 11.532 | cum | S-104 R2 | |
| 28-10-2026 | 3.2 | Beams B7 to B10, below slab | 4 | 6.20 | 0.25 | 0.300 | 1.860 | cum | S-104 R2 | |
| 28-10-2026 | 3.2 | Less duct opening | -1 | 1.20 | 0.90 | 0.150 | -0.162 | cum | S-104 R2 | Deduction |
| 3.2 | Total this entry | 13.230 | cum |
When the measurement sheet is used
Whenever work is measured. Each abstract line in the RA bill points to one or more pages of the measurement sheet.
- One row per location, so the client's engineer can find it on the drawing.
- Enter deductions with negative nos. The total then adds up in one column.
- Record the drawing number and revision. Most quantity queries are revision queries.
RCC M25 in slabs and beams
LocationNosLBDQtySlab S3, bay 2 to 4112.406.200.15011.53Beams B7 to B1046.200.230.4502.57Less duct opening11.200.900.150-0.16Total this entry13.94
Hadapsar site · 28 Oct, 4:12 pm · 3 photosSend for approval