Free download, CSV for Excel

Material reconciliation template for contractors

A reconciliation of client-issued steel or cement: issued, at site, consumed, theoretical consumption, the permitted variation and any recovery for excess.

Columns and filled rows

All 10 columns, filled from one work order so the arithmetic can be checked. The download opens in Excel, Google Sheets or LibreOffice.

Download the template

When the material reconciliation is used

When the client issues cement or steel to the contractor and recovers any consumption above the theoretical quantity, usually at a penal rate set in the contract.

  • Theoretical consumption comes from the billed quantities: here 43,115 kg of reinforcement billed up to RA 6.
  • Consumed is issued minus stock at site, verified jointly.
  • Allowed is theoretical plus the variation in your contract: 14.000 x 1.025 = 14.350 MT.

See the RA bill generator