Scheduling · XML or Excel file exchange
Microsoft Project task mapping for billing
Map Microsoft Project tasks to BOQ items, then send measured progress back as a sheet for the schedule update.
Data that moves each way
Only these items move, only for the work orders you turn on.
- From Microsoft Project
Task list with IDs, names and outline levels, from an XML or Excel export
In - To Microsoft Project
Measured quantity and per cent complete per task, as an Excel sheet
Out
Field mapping. Tatha Vastu to Microsoft Project.
Field mapping · Tatha Vastu to Microsoft Project
| Tatha Vastu | Microsoft Project |
|---|---|
| BOQ item | Task ID |
| Work order section | Summary task |
| Per cent of BOQ executed | Per cent complete |
| Measured quantity to date | Custom number field |
Setup in 4 steps
- Save the schedule from Microsoft Project as XML or export the task table to Excel, then upload it under Integrations.
- Map each task to one or more BOQ items. Outline levels help group tasks by floor or section.
- Each month, download the progress sheet with per cent complete per task.
- Import the sheet into Microsoft Project with its import map to update progress.
Set up Microsoft Project
- 1. Save the schedule from Microsoft Project as XML or export the task table to Excel, then upload it under Integrations.Done
- 2. Map each task to one or more BOQ items. Outline levels help group tasks by floor or section.Done
- 3. Each month, download the progress sheet with per cent complete per task.Done
- 4. Import the sheet into Microsoft Project with its import map to update progress.Now
Do we need Project Online or a server?
No. The desktop app's XML and Excel import and export are enough.
Can several BOQ items roll into one task?
Yes. The task's per cent complete is weighted by the value of each mapped item.
Does it change our baseline?
No. The progress sheet updates per cent complete only. Baselines stay as you set them.
Can we use both Primavera P6 and Microsoft Project?
Yes, on different work orders. Each work order maps to one schedule.